WORK PARTY TWO OF TWO – BYWASH BRIDGING
The second, smaller group of volunteers stayed in the Hidden Lock site to start on constructing a new crossing of the temporary by-wash. This is needed to provide safer, sturdier, easier vehicular access to the far side of the site. The first phase is to reinforce the by-wash with a concrete base and block walls.
Concrete was mixed and carefully laid in the bottom of the by-wash. An impermeable rubber membrane was added to both ends of the slab. Before the concrete had a chance to harden, the first row of concrete blocks was set into the slab. The wall will be completed at a later date, followed by the bridge itself.
|
2 comments
Michael Coulter says:
Dec 5, 2019
The lads worked hard, nearly a ton of concrete laid, well done
Michael Coulter says:
Dec 5, 2019
Nice to see a cleared garden, you all must have worked hard have a pat on the back from me. It can be very rewarding helping somebody in that way. Hope he can do something with it before all the weeds grow again