Clydach Lock Work Party; 26.9.17.
The relaying and cementing of the coping stones began today. Rhodri from the Canal And River Trust could only start as soon as the lime mortar mix arrived by tractor and trailer. Cementing work was also underway at the Old Highways Depot fifty yards up the canal so a shuttle service with Gareth at the wheel brought the necessary mix down to us. 
By close of play we had completed about half the necessary cementing with all the sleepers in that half now in their exact position ready for bolts to be drilled into them and the supporting timbers.
The second half will not be so easy as we have missing coping stones at that end and their replacements will need some cutting and paring down to fit the gaps.
Recent Post
Work Party: Tuesday 23rd June 2026
Phew, what a scorcher! With the mercury creeping up to 30ºC and high humidity a smallish group of ...
Read More The Week Ahead: Sunday 21st – Saturday 27th June 2026
Sunday 21st June: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last boat ...
Read More Work Party: Tuesday 16th June 2026
Weather-wise, today started off with a bit of drizzle that soon passed leaving the morning oppressively muggy. Most ...
Read More The Week Ahead: Sunday 14th – Saturday 20th June 2026
Sunday 14th June: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last boat ...
Read More Work Party: Tuesday 9th June 2026
Today's gathering offered a range of tasks for our volunteers - there was something for every taste at ...
Read More The Week Ahead: Sunday 7th – Saturday 13th June 2026
Sunday 7th June: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last boat ...
Read More