The “Hidden Lock” in Cydach – Progress Report, March 2024

The “Hidden Lock” in Cydach – Progress Report, March 2024

Gill luckily was passing the Buried Lock in Clydach as some of the culvert was being pulled out. What is let of the original 1798 lock wall is in good condition but, sadly, most of the walls were not conserved when the lock was buried.

It is truly wonderful to see major work underway on Phase Two of the restoration project. Our vision for a fully functioning Clydach Lock No. 7 is one step closer to reality.

Funded by The Shared Prosperity Fund that is part of the UK Government’s levelling-up agenda, and is administered by Swansea Council.

Recent Post

Work Party: Tuesday 14th April 2026

A bit chilly but dry save for a couple of very brief showers for today's exertions that proved ...
Read More

The Week Ahead: Sunday 12th – Saturday 18th April 2026

Sunday 12th April: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last boat ...
Read More

Work Party: Tuesday 7th April 2026

The warmest day of the year so far and the volunteers met at the Swansea Canal Centre to ...
Read More

The Week Ahead: Sunday 5th – Saturday 11th April 2026

  Sunday 5th April: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last ...
Read More

Work Party: Tuesday 31st March 2026

Today was essentially a repeat of last week. A slightly different sub-set of volunteers continued a range of ...
Read More

The Week Ahead: Sunday 29th March – Saturday 4th April 2026

Tuesday 31st March: Work Party: Those wishing to eat breakfast should meet at the Roadhouse Cafe in Clydach ...
Read More