Clydach Lock Work Party; 26.9.17.
The relaying and cementing of the coping stones began today. Rhodri from the Canal And River Trust could only start as soon as the lime mortar mix arrived by tractor and trailer. Cementing work was also underway at the Old Highways Depot fifty yards up the canal so a shuttle service with Gareth at the wheel brought the necessary mix down to us. 
By close of play we had completed about half the necessary cementing with all the sleepers in that half now in their exact position ready for bolts to be drilled into them and the supporting timbers.
The second half will not be so easy as we have missing coping stones at that end and their replacements will need some cutting and paring down to fit the gaps.
Recent Post
Work Party: Tuesday 9th June 2026
Today's gathering offered a range of tasks for our volunteers - there was something for every taste at ...
Read More The Week Ahead: Sunday 7th – Saturday 13th June 2026
Sunday 7th June: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last boat ...
Read More Work Party: Tuesday 2nd June 2026
The weather forecast for today was grim so we decided to abandon plans for concreting and instead returned ...
Read More The Week Ahead: Sunday 31st May – Saturday 6th June 2026
Sunday 31st May: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last ...
Read More Work Party: Tuesday 26th May 2026
Phew, what a scorcher! With the mercury hovering around 30°C we took to the relative shade offered by ...
Read More Summer Fair 2026
We are delighted to announce our Summer Fair for 2026. Join us at the Swansea Canal Centre for ...
Read More