Clydach Lock Work Party; 26.9.17.

20170926_170913

Clydach Lock Work Party; 26.9.17.

20170926_170913

The relaying and cementing of  the coping stones began today. Rhodri from the Canal And River Trust could only start as soon as the lime mortar mix arrived by tractor and trailer. Cementing work was also underway at the Old  Highways Depot fifty yards up the canal so a shuttle service with Gareth at the wheel brought the necessary mix down to us. 20170926_171804

20170926_131558    By close of play we had completed about half the necessary cementing with all the sleepers in that half now in their exact position ready for bolts to be drilled into them and the supporting timbers.

 

The second half will not be so easy as we have missing coping stones at that end and their replacements will need some cutting and paring down to fit the gaps.

Recent Post

Work Party: Tuesday 4th November 2025

There was a fantastic turn-out of volunteers today at the Swansea Canal Centre, made all the more amazing ...
Read More

“Spooky” – 2nd November 2025

A bright day saw the 2025 season of canoe and kayak hire draw to a close with our ...
Read More

Christmas Quiz 2025, Thursday 11th December, 7pm.

Join us for our second annual Christmas Quiz. Full details in the poster. Remember to purchase your tickets ...
Read More

The Week Ahead: Sunday 2nd – Saturday 8th November 2025

Sunday 2nd November: “Spooky” in Coed Gwilym Park. The grand finale of canoe and kayak hire for 2025. ...
Read More

Work Party: Tuesday 28th October 2025

This week, the volunteers returned to the Swansea Canal Centre to continue to create the community garden. The ...
Read More

Local History Book Fair, Swansea Museum, 8th November 2025

The Royal Institution of Wales is holding its annual Local History Book Fair in the Swansea Museum on ...
Read More