WORK PARTY SOUTH OF PONTARDAWE PLAYING FIELDS: 2.5.17.

REPAIRING ERODED BANKS.

WORK PARTY SOUTH OF PONTARDAWE PLAYING FIELDS: 2.5.17.

 

We are halfway to rebuilding the tow-path edges south of the 800 yard piped section at Pontardawe Playing Fields. This  restoration will prevent further erosion of the banks  and any subsequent flooding.  Most of the material used is provided by the Canal and River Trust though much of the local Blue Tennant Sandstone is recovered from the canal itself.

IMG_20170503_085528

The base layer of sand bags filled with stone dust and cement is built up with the stone and it is a jugsaw puzzle technique from then on, finishing with the flat coping stones at the top as the ‘side pieces’.

 

 

 

 

The ‘masons’ building the wall send the messages back to the ‘quarry’ if it is ‘thin flat’ or fat flat’ stone that is required to finish the top layer, and it is up to the wheelbarrow haulers to  load the barrows with the appropriate stone for them. We hope to buy a mini-tractor soon that will be narrow enough to use the towpath and  reduce the need for manually humping  very heavy barrows of stone and lime mortar mix.

 

In the photo below, the mix has just been delivered and David, the wall builder, appears to be indicating the size of the stone he wants. Either that, or he has had a bad attack of indigestion.

 

 

 

IMG_20170502_095658195

 

IMG_20170503_085655

 

 

 

 

 

 

It is work done in the open air and in some beautiful spots. All our volunteers are made welcome and enjoy the camaraderie, banter, and refreshments provided.

On average, some twenty five men and women join us each Tuesday. There is great satisfaction to be had from improving and maintaining our wonderful canal and we are blessed  here to have such a lovely waterway in our community to use, treasure and enjoy.

Recent Post

The Week Ahead: Sunday 26th July – Saturday 1st August 2026

Sunday 26th July: Canoes & Kayaks HIRE IS CANCELLED. Please accept our apologies for the inconvenience.. Tuesday 28th ...
Read More

Work Party: Tuesday 21st July 2026

Another scorching day for another session of canal clearing between the Canal Centre and Pont John. We were ...
Read More

The Week Ahead: Sunday 19th – Saturday 25th July 2025

Sunday 19th July: Canoes & Kayaks for hire at Coed Gwilym Park, Clydach. First hire 10am, last boat ...
Read More

Work Party: Tuesday 14th July 2026

Our volunteers split again this week across two locations, the Buried Lock and the Pont John area in ...
Read More

Green Flag Community Award 2026/2027

We've done it again! We have been awarded the Green Flag Community Award for the eleventh year. We ...
Read More

Canoe & Kayak Hire [Fridays]

The Friday sessions of canoe and kayak hire run from 24th July to 28th August First hire is ...
Read More